200 cards to draw from

ACommon occupational skills22
BInspects and maintains crane42
CCrane set-up, hoisting calculations and lift planning46
DRigging34
EOperates crane56

Your rounds

Kept on this device
Average79%
Best100%

Checking

What a checked pair looks like
Browse the 20 free cards and explanations

A planned delivery area has adequate bearing capacity, but stacked loads there would block the site's only emergency exit. A second approved area has adequate capacity and preserves that exit. Which landing arrangement is justified?

Answer: Use the second approved area and keep the emergency exit clear.

A safe placement area must preserve emergency access as well as support the load. Both areas carry the load, but only the second preserves the sole exit, so bearing capacity alone cannot select the first.

Exam trap: Using the first area because its slab is adequate ignores the emergency route that the stored load would block.

Standard reference: RSOS 2023 A-1.01.06P

Before a lift, the agreed radio channel is continuously occupied by another crew's unrelated traffic. A tested alternate channel is available to every lift-team member. How should communication be arranged?

Answer: Agree on the alternate channel with the whole lift team and complete a radio check before lifting.

The whole lift team needs one functioning, agreed communication arrangement. Coordinating the change and testing every required link establishes it before movements depend on radio directions.

Exam trap: Changing only the operator's radio would leave the signaller on the old channel.

Standard reference: RSOS 2023 A-2.01.11P

Why must a crane hook with a permanently enlarged throat be assessed instead of simply hammered back to its original shape?

Answer: Restoring shape does not establish that the deformed hook retains its required strength and integrity.

A permanently distorted hook has undergone a material or loading event needing the specified rejection assessment. Returning its outline to the old shape cannot prove its internal condition or rated strength.

Exam trap: Hammering the hook until its throat dimension passes hides the deformation without establishing structural integrity.

Standard reference: RSOS 2023 B-3.03.09P

During a dry pre-operational check, the cab windshield is clear but its wipers fail to move when tested. Rain is forecast during the shift. How should the finding be handled?

Answer: Report the failed wipers and resolve the defect under the crane's operating and maintenance requirements.

Functional checks test whether cab components work when needed. Clear glass in dry conditions does not establish that failed wipers can maintain visibility in the forecast rain.

Exam trap: Waiting until rain begins defers a known defect until it affects visibility during operation.

Standard reference: RSOS 2023 B-3.08.06P

Why must a running hoist rope be observed from a safe position rather than grasped to feel for broken wires?

Answer: The moving rope can drag the hand into a sheave or drum, in addition to cutting it.

A moving rope creates an entanglement and drawing-in hazard near rotating equipment. Monitoring must preserve distance and use the approved observation and inspection procedure.

Exam trap: Gloves can reduce cuts but do not prevent the hand or glove being drawn into a sheave or drum.

Standard reference: RSOS 2023 B-4.03.02L

Why is a warning tag alone insufficient where a crane maintenance procedure requires personal lockout of an isolating device?

Answer: The tag warns others, but does not physically prevent operation of the isolating device.

A lock provides a physical barrier to operating the isolation device. A tag communicates status but is not that physical restraint; use the complete required lockout procedure.

Exam trap: Assuming that a prominent warning tag has the same function as a personal lock omits the required physical control.

Standard reference: RSOS 2023 B-5.01.02P

Why must the final building layout be considered when planning the assist crane's position for tower-crane dismantling?

Answer: The completed structure may obstruct the assist crane's access, setup or required pick reach.

Access used during erection can disappear as construction progresses. The assist crane still needs an adequate setup and a rated reach to every planned dismantling pick.

Exam trap: Reusing the erection setup assumes the completed building has not changed access or reach.

Standard reference: RSOS 2023 C-6.02.02L

Before a bottom climb, reinforcing bars protrude into the approved mast opening. Their structural purpose is unknown. What must happen before the climb can begin?

Answer: Have the interference resolved through the authorized structural and climbing plan; do not cut the bars on assumption.

The climbing envelope must be clear, but reinforcing bars may be structural. The conflict must be resolved through authorized site engineering and the climbing plan before movement begins.

Exam trap: Cutting the obstruction immediately could damage the building structure supporting the crane.

Standard reference: RSOS 2023 C-7.01.04P

Why must the tower crane's climbing sequence specify when ordinary crane motions are prohibited?

Answer: Intermediate support and balance arrangements may not safely resist ordinary crane movements.

Intermediate climbing states can have a different load path and balance from the finished crane. The sequence controls which movements may occur while support is transferred.

Exam trap: The normal working load chart does not by itself authorize ordinary motion during an intermediate climbing state.

Standard reference: RSOS 2023 C-7.02.02L

A negligible-mass frame carries 300 kg at x = 0 m and 900 kg at x = 4 m. Using x(CoG) = sum(mass × position) ÷ total mass, where is the combined centre of gravity?

Answer: At x = 3.0 m: (300 × 0 + 900 × 4) ÷ 1 200.

The combined centre follows the mass-weighted position: (300 × 0 + 900 × 4) ÷ (300 + 900) = 3.0 m. Both component masses enter the denominator.

Exam trap: The geometric midpoint at 2 m ignores the unequal component masses.

Standard reference: RSOS 2023 C-8.01.03L

A landing floor's total load allowance exceeds a machine's weight, but that allowance assumes distributed loading. The machine rests on two small feet and their local bearing has not been checked. What remains unresolved?

Answer: Whether the floor and planned supports can carry the concentrated reactions at the feet.

A distributed rating describes a load spread over an area. Small feet concentrate reactions locally, so the actual floor and support arrangement must be assessed for those concentrated demands.

Exam trap: Dividing the machine weight by the whole floor area conceals the high reactions beneath its two feet.

Standard reference: RSOS 2023 C-8.03.01L

A sewn web sling has no cuts in its main web and its tag is legible. Several stitches joining the load-bearing eye are broken. Does the sound-looking web establish that it is usable?

Answer: No. The damaged load-bearing stitching requires removal and assessment under the sling's rejection criteria.

The eye stitching is part of this sling's load-bearing construction. Intact main web and a readable tag do not compensate for broken structural stitching.

Exam trap: Treating the tag and uncut web as a complete inspection overlooks the damaged connection that forms the eye.

Standard reference: RSOS 2023 D-9.01.03P

Why is chain diameter alone insufficient to select a chain sling for overhead lifting?

Answer: Its chain grade, construction, fittings and approved lifting rating also determine suitability.

Chains of the same size can differ in grade, construction and intended duty. The complete rated sling and its fittings must be appropriate for overhead lifting.

Exam trap: Selecting ordinary chain solely by link thickness ignores its material grade and approved application.

Standard reference: RSOS 2023 D-10.01.01L

Why must a rigger avoid the space between a suspended load and a nearby fixed structure?

Answer: A small unplanned load movement can create a crushing or trapping point.

The danger is relative motion between the load and an immovable boundary. Even a small swing or shift can eliminate the handler's escape space.

Exam trap: Standing there because the present gap looks adequate assumes the suspended load cannot move unexpectedly.

Standard reference: RSOS 2023 D-10.03.01P

Why does a successful morning motion test not, by itself, establish the structural integrity of the whole crane?

Answer: It verifies the tested functions; structural condition needs its required inspections and certification.

A functional test observes controls, brakes and limiting devices. A crane can respond correctly while a structural defect remains undetected, so the required structural inspections and certification remain separate.

Exam trap: Treating smooth motion as proof of sound structural members exceeds what the motion test actually observes.

Standard reference: RSOS 2023 E-11.01.01L

A load extends 2.5 m inward from its hook. On the same radial line, a scaffold reaches 11 m from the slew axis. The lift plan requires 1 m clearance. What minimum hook radius keeps the load outside that scaffold?

Answer: 14.5 m.

The innermost load edge is hook radius minus 2.5 m. It must remain at least 11 + 1 = 12 m from the axis, so the hook must remain at or beyond 12 + 2.5 = 14.5 m.

Exam trap: A 12 m hook radius clears the hook but places the load edge at 9.5 m, inside the scaffold envelope.

Standard reference: RSOS 2023 E-12.01.06P

What does a crane's slewing gear reduction do to motor speed and torque at the slew ring?

Answer: It reduces speed and increases torque, allowing for losses.

Reduction gearing trades rotational speed for torque. The slew ring turns more slowly than the motor, while torque is increased by the reduction ratio less mechanical losses.

Exam trap: Assuming the reduction increases speed and torque together reverses its speed effect and ignores conservation of power.

Standard reference: RSOS 2023 E-12.03.01L

A tandem lift has an approved emergency set-down bay. Before the pick, pallets are delivered into that bay. The normal destination remains clear. What must be resolved before starting?

Answer: Restore the planned emergency bay or obtain and brief an approved alternative.

A contingency landing must remain usable if the normal sequence is interrupted. Remove the obstruction or obtain an approved alternative and brief the crew before starting; the clear normal destination does not replace the emergency provision.

Exam trap: Starting because the normal landing is clear assumes no interruption will require the blocked contingency bay.

Standard reference: RSOS 2023 E-13.01.02P

A personnel basket passes inspection and its two-way radio works. At a recessed work location, workers cannot reach the planned rescue landing, and the rescue kit cannot reach the basket. What must be resolved before occupied lifting?

Answer: A workable rescue arrangement for that location.

Rescue must be feasible at the actual occupied location. A sound basket and working radio cannot overcome an unreachable landing or insufficient equipment reach. Resolve and brief a workable recovery arrangement first.

Exam trap: Radio contact can report the emergency but supplies no physical means of recovering the occupants.

Standard reference: RSOS 2023 E-13.03.07P

A luffing crane is at its specified parking radius with both slew brakes released. No obstacle touches it, but an approved free-slew check shows excessive resistance through every heading. What system condition still needs investigation?

Answer: Excessive internal resistance in the slew mechanism.

Free slewing depends on the full mechanical drive path. With both brakes released and contact excluded, excessive internal resistance calls for qualified assessment of the slew motors, gearboxes and bearing.

Exam trap: Releasing the already verified brakes again does not explain resistance elsewhere in the mechanism.

Standard reference: RSOS 2023 E-14.02.06P