MathOnline Red Seal Exam Preparation, built on official standards
Boilermaker formula sheet, conversions and acronyms
MathReference20 formulas · 50 conversions · 12 acronyms
On the exam
- Official formula sheet
- Given at the exam
- Conversions
- Not given: learn them
- Acronyms
- You get the list
- Calculator
- The same calculator as here
On the exam
Formula sheetGiven at the exam
CalculatorThe same as here
Formulas
20 formulasFrom the official Boilermaker formula sheet. The same sheet is printed for you at the exam.
π = 3.1416
Arc length = radius × degrees × 0.01745
Arc length = (central angle in degrees × circumference) / 360°
Area of circle = A = π r2
Area of rectangle = L × W
C = π d or C = 2 π r
Clip spacing = 6 D
Drum capacity = ( A + B ) × B × C × F
Factors for angle of cut = (angle of turn) / (number of welds × 2)
Lead line pull = (weight) / (ratio)
Length of bolt = length of grip + washer THK + nut THK + 2 threads
Mean diameter = OD − wall thickness = ID + wall thickness
Number of wire rope clips = 3 D + 1
Pythagorean theorem = a2 + b2 = c2
Sling tension = (weight) / (number) × (length) / (vertical length)
Tube expansion = clearance + tube reduction + tube ID
V - block opening for a 90° air bend on heavier plate = 10 × THK of PL
Volume of cube = L × W × H
Working load limituse the specified rope/hardware rating and configuration.
Wrench size = 1 (1) / (2) × bolt size + (1) / (8) in.
Additional formulas and constants
π = 3.1416
Arc length = radius × degrees × 0.01745
Arc length = (central angle in degrees × circumference) / 360°
Area of circle = A = π r2
Area of rectangle = L × W
C = π d or C = 2 π r
Clip spacing = 6 D
Drum capacity = ( A + B ) × B × C × F
Factors for angle of cut = (angle of turn) / (number of welds × 2)
Lead line pull = (weight) / (ratio)
Length of bolt = length of grip + washer THK + nut THK + 2 threads
Mean diameter = OD − wall thickness = ID + wall thickness
Number of wire rope clips = 3 D + 1
Pythagorean theorem = a2 + b2 = c2
Sling tension = (weight) / (number) × (length) / (vertical length)
Tube expansion = clearance + tube reduction + tube ID
V - block opening for a 90° air bend on heavier plate = 10 × THK of PL
Volume of cube = L × W × H
Working load limituse the specified rope/hardware rating and configuration.
Wrench size = 1 (1) / (2) × bolt size + (1) / (8) in.
On the exam
ConversionsNot given: learn them
Conversions
50 conversions1 in25.4 mm
1 ft304.8 mm
1 ft0.3048 m
1 yd0.9144 m
1 m3.281 ft
1 m39.37 in
1 km0.6214 mi
1 mi1.609 km
1 kg2.205 lb
1 lb0.4536 kg
1 lb16 oz
1 oz28.35 g
1 t (tonne)1 000 kg
1 t (tonne)2 205 lb
1 short ton2 000 lb
1 short ton907.2 kg
Water1 000 kg/m³ = 1 kg/L
Water62.4 lb/ft³
Water8.34 lb per US gal
Water10.0 lb per imp gal
Steel7 850 kg/m³ = 490 lb/ft³
Steel plate7.85 kg per m² per mm
Concrete2 400 kg/m³ = 150 lb/ft³
1 kg/m³0.06243 lb/ft³
1 lb/ft³16.02 kg/m³
1 psi6.895 kPa
1 kPa0.1450 psi
1 bar100 kPa
1 bar14.50 psi
1 atm101.3 kPa
1 atm14.70 psi
1 in w.c.249.1 Pa
1 ft of water0.4335 psi
1 in Hg3.386 kPa
1 lbf4.448 N
1 kN224.8 lbf
1 ft²144 in²
1 ft²0.0929 m²
1 m²10.76 ft²
1 yd²9 ft²
1 yd²0.8361 m²
1 ha10 000 m²
1 ha2.471 acres
1 acre4 047 m²
°C to °F× 1.8, then + 32
°F to °C− 32, then ÷ 1.8
°C to K+ 273.15
A difference of 1 °C1.8 °F
Water freezes0 °C = 32 °F
Water boils (sea level)100 °C = 212 °F
Length
1 in25.4 mm
1 ft304.8 mm
1 ft0.3048 m
1 yd0.9144 m
1 m3.281 ft
1 m39.37 in
1 km0.6214 mi
1 mi1.609 km
Mass
1 kg2.205 lb
1 lb0.4536 kg
1 lb16 oz
1 oz28.35 g
1 t (tonne)1 000 kg
1 t (tonne)2 205 lb
1 short ton2 000 lb
1 short ton907.2 kg
Density and unit mass
Water1 000 kg/m³ = 1 kg/L
Water62.4 lb/ft³
Water8.34 lb per US gal
Water10.0 lb per imp gal
Steel7 850 kg/m³ = 490 lb/ft³
Steel plate7.85 kg per m² per mm
Concrete2 400 kg/m³ = 150 lb/ft³
1 kg/m³0.06243 lb/ft³
1 lb/ft³16.02 kg/m³
Pressure and force
1 psi6.895 kPa
1 kPa0.1450 psi
1 bar100 kPa
1 bar14.50 psi
1 atm101.3 kPa
1 atm14.70 psi
1 in w.c.249.1 Pa
1 ft of water0.4335 psi
1 in Hg3.386 kPa
1 lbf4.448 N
1 kN224.8 lbf
Area
1 ft²144 in²
1 ft²0.0929 m²
1 m²10.76 ft²
1 yd²9 ft²
1 yd²0.8361 m²
1 ha10 000 m²
1 ha2.471 acres
1 acre4 047 m²
Temperature
°C to °F× 1.8, then + 32
°F to °C− 32, then ÷ 1.8
°C to K+ 273.15
A difference of 1 °C1.8 °F
Water freezes0 °C = 32 °F
Water boils (sea level)100 °C = 212 °F
On the exam
AcronymsYou get the list
Acronyms
12 acronymsThe following acronyms used in this trade may be on its Red Seal exam. They will also be provided with the exam sitting. The official list (PDF)
FRPfibreglass reinforced plastic
GTAWgas tungsten arc welding
HEPAhigh-efficiency particulate air
IDinside diameter
IWRCindependent wire rope core
ODoutside diameter
OH&SOccupational Health and Safety
PPEpersonal protective equipment
SCBAself-contained breathing apparatus
SDSsafety data sheet
UVultra violet
WLLworking load limit
FRPfibreglass reinforced plastic
GTAWgas tungsten arc welding
HEPAhigh-efficiency particulate air
IDinside diameter
IWRCindependent wire rope core
ODoutside diameter
OH&SOccupational Health and Safety
PPEpersonal protective equipment
SCBAself-contained breathing apparatus
SDSsafety data sheet
UVultra violet
WLLworking load limit