MathOnline Red Seal Exam Preparation, built on official standards
Transport Trailer Technician formula sheet, conversions and acronyms
MathReference40 formulas · 56 conversions · 8 acronyms
On the exam
- Official formula sheet
- None for this trade
- Conversions
- Not given: learn them
- Acronyms
- You get the list
- Calculator
- The same calculator as here
On the exam
Formula sheetNone for this trade
CalculatorThe same as here
Formulas
40 formulasThe Red Seal Program does not publish a formula sheet for this trade, so these are the formulas its math lessons use.
°F = 1.8 × °C + 32
°C = (°F − 32) / 1.8
K = °C + 273.15
Δ°F = 1.8 × Δ°C
1 US gal = 3.785411784 L; 1 Imperial gal = 4.54609 L
RectangleA = LW; perimeter = 2(L+W)
TriangleA = bh/2; perimeter = a+b+c
CircleA = πr² = πd²/4; C = πd
BoxV = LWH
CylinderV = πr²h
SphereV = 4πr³/3
Cone or pyramidV = base area × h/3
Triangular wedgeV = LWH/2
1 m³ = 1000 L
Cylinder side = 2πrh
Cylinder with one end = 2πrh + πr²
Closed cylinder = 2πrh + 2πr²
Closed box = 2(LW + LH + WH)
Open box = LW + 2LH + 2WH
Sphere = 4πr²
Cone lateral area = πrs
Pyramid lateral area = perimeter of base × slant height / 2
c² = a² + b²
sin θ = opposite/hypotenuse
cos θ = adjacent/hypotenuse
tan θ = opposite/adjacent
θ = atan(rise/run)
Offset travel = offset / sin θ
Arc length = πrθ/180 = πdθ/360
Sector pattern angle = 360 × base radius / slant radius
Equivalent formpattern angle = 180 × base diameter / slant radius
Grade (%) = rise/run × 100
Rise = run × unit rise/unit run
Symmetrical roof run = span/2
Rafter line length = √(run² + rise²)
Unit line length (per 12 of run) = √(12² + unit rise²)
New quantity = original quantity × scale factor
Scale factor = required yield / original yield
With p% addedfinal = original × (1+p/100)
Baker’s percentage = ingredient mass / flour mass × 100
Temperature and unit conversion
°F = 1.8 × °C + 32
°C = (°F − 32) / 1.8
K = °C + 273.15
Δ°F = 1.8 × Δ°C
1 US gal = 3.785411784 L; 1 Imperial gal = 4.54609 L
Areas, perimeter and circumference
RectangleA = LW; perimeter = 2(L+W)
TriangleA = bh/2; perimeter = a+b+c
CircleA = πr² = πd²/4; C = πd
Volumes, capacity and material quantities
BoxV = LWH
CylinderV = πr²h
SphereV = 4πr³/3
Cone or pyramidV = base area × h/3
Triangular wedgeV = LWH/2
1 m³ = 1000 L
Surface area of vessels and insulation
Cylinder side = 2πrh
Cylinder with one end = 2πrh + πr²
Closed cylinder = 2πrh + 2πr²
Closed box = 2(LW + LH + WH)
Open box = LW + 2LH + 2WH
Sphere = 4πr²
Cone lateral area = πrs
Pyramid lateral area = perimeter of base × slant height / 2
Pythagoras, trigonometry and offsets
c² = a² + b²
sin θ = opposite/hypotenuse
cos θ = adjacent/hypotenuse
tan θ = opposite/adjacent
θ = atan(rise/run)
Offset travel = offset / sin θ
Arc lengths and developed patterns
Arc length = πrθ/180 = πdθ/360
Sector pattern angle = 360 × base radius / slant radius
Equivalent formpattern angle = 180 × base diameter / slant radius
Grade, roof rise and run
Grade (%) = rise/run × 100
Rise = run × unit rise/unit run
Symmetrical roof run = span/2
Rafter line length = √(run² + rise²)
Unit line length (per 12 of run) = √(12² + unit rise²)
Percentages, recipe scaling and quantities
New quantity = original quantity × scale factor
Scale factor = required yield / original yield
With p% addedfinal = original × (1+p/100)
Baker’s percentage = ingredient mass / flour mass × 100
On the exam
ConversionsNot given: learn them
Conversions
56 conversions1 kg2.205 lb
1 lb0.4536 kg
1 lb16 oz
1 oz28.35 g
1 t (tonne)1 000 kg
1 t (tonne)2 205 lb
1 short ton2 000 lb
1 short ton907.2 kg
1 psi6.895 kPa
1 kPa0.1450 psi
1 bar100 kPa
1 bar14.50 psi
1 atm101.3 kPa
1 atm14.70 psi
1 in w.c.249.1 Pa
1 ft of water0.4335 psi
1 in Hg3.386 kPa
1 lbf4.448 N
1 kN224.8 lbf
1 N·m0.7376 lb·ft
1 N·m8.851 lb·in
1 lb·ft1.356 N·m
1 lb·ft12 lb·in
1 lb·in0.1130 N·m
1 kgf·m9.807 N·m
1 in25.4 mm
1 ft304.8 mm
1 ft0.3048 m
1 yd0.9144 m
1 m3.281 ft
1 m39.37 in
1 km0.6214 mi
1 mi1.609 km
Power (W)V × A
1 kW1 000 W
1 kVA1 000 VA
1 hp746 W
1 mA0.001 A
1 mV0.001 V
1 kΩ1 000 Ω
1 MΩ1 000 000 Ω
1 kWh1 kW for 1 hour
1 ft²144 in²
1 ft²0.0929 m²
1 m²10.76 ft²
1 yd²9 ft²
1 yd²0.8361 m²
1 ha10 000 m²
1 ha2.471 acres
1 acre4 047 m²
°C to °F× 1.8, then + 32
°F to °C− 32, then ÷ 1.8
°C to K+ 273.15
A difference of 1 °C1.8 °F
Water freezes0 °C = 32 °F
Water boils (sea level)100 °C = 212 °F
Mass
1 kg2.205 lb
1 lb0.4536 kg
1 lb16 oz
1 oz28.35 g
1 t (tonne)1 000 kg
1 t (tonne)2 205 lb
1 short ton2 000 lb
1 short ton907.2 kg
Pressure and force
1 psi6.895 kPa
1 kPa0.1450 psi
1 bar100 kPa
1 bar14.50 psi
1 atm101.3 kPa
1 atm14.70 psi
1 in w.c.249.1 Pa
1 ft of water0.4335 psi
1 in Hg3.386 kPa
1 lbf4.448 N
1 kN224.8 lbf
Torque
1 N·m0.7376 lb·ft
1 N·m8.851 lb·in
1 lb·ft1.356 N·m
1 lb·ft12 lb·in
1 lb·in0.1130 N·m
1 kgf·m9.807 N·m
Length
1 in25.4 mm
1 ft304.8 mm
1 ft0.3048 m
1 yd0.9144 m
1 m3.281 ft
1 m39.37 in
1 km0.6214 mi
1 mi1.609 km
Electrical
Power (W)V × A
1 kW1 000 W
1 kVA1 000 VA
1 hp746 W
1 mA0.001 A
1 mV0.001 V
1 kΩ1 000 Ω
1 MΩ1 000 000 Ω
1 kWh1 kW for 1 hour
Area
1 ft²144 in²
1 ft²0.0929 m²
1 m²10.76 ft²
1 yd²9 ft²
1 yd²0.8361 m²
1 ha10 000 m²
1 ha2.471 acres
1 acre4 047 m²
Temperature
°C to °F× 1.8, then + 32
°F to °C− 32, then ÷ 1.8
°C to K+ 273.15
A difference of 1 °C1.8 °F
Water freezes0 °C = 32 °F
Water boils (sea level)100 °C = 212 °F
On the exam
AcronymsYou get the list
Acronyms
8 acronymsThe following acronyms used in this trade may be on its Red Seal exam. They will also be provided with the exam sitting. The official list (PDF)
ABSanti-braking system
ACair-conditioning
ECUelectronic control unit
LEDlight-emitting diode
OEMoriginal equipment manufacturer
PPVpressure protection valve
RPMrotations per minute
TXVthermostatic expansion valve
ABSanti-braking system
ACair-conditioning
ECUelectronic control unit
LEDlight-emitting diode
OEMoriginal equipment manufacturer
PPVpressure protection valve
RPMrotations per minute
TXVthermostatic expansion valve