Formulas

8 formulas

From the official Powerline Technician formula sheet. The same sheet is printed for you at the exam.

Compressive force = ( tension × (height) / (length) )
Conductor tension = (conductor weight × span2) / (8 × sag)
Conductor weight = (span A + span B) / (2) × weight per unit × SF
kVA = (( V1 × I1 ) + ( V2 × I2 )) / (1 000)
Pull = (weight + ( 10% weight × # of sheaves )) / (MA)
Ratio = primary voltage ÷ secondary voltage
Ruling span = average span + (2) / (3) ( maximum span – average span )
WYE phase-to-phase voltage = phase-to-ground voltage × 1.73
Additional formulas and constants
Compressive force = ( tension × (height) / (length) )
Conductor tension = (conductor weight × span2) / (8 × sag)
Conductor weight = (span A + span B) / (2) × weight per unit × SF
kVA = (( V1 × I1 ) + ( V2 × I2 )) / (1 000)
Pull = (weight + ( 10% weight × # of sheaves )) / (MA)
Ratio = primary voltage ÷ secondary voltage
Ruling span = average span + (2) / (3) ( maximum span – average span )
WYE phase-to-phase voltage = phase-to-ground voltage × 1.73

On the exam

ConversionsNot given: learn them

Conversions

58 conversions
Power (W)V × A
1 kW1 000 W
1 kVA1 000 VA
1 hp746 W
1 mA0.001 A
1 mV0.001 V
1 kΩ1 000 Ω
1 MΩ1 000 000 Ω
1 kWh1 kW for 1 hour
1 hp746 W
1 kW1.341 hp
1 kW3 412 Btu/h
1 Btu/h0.2931 W
1 Btu1.055 kJ
1 ton of refrigeration12 000 Btu/h
1 ton of refrigeration3.517 kW
1 kWh3.6 MJ
1 therm100 000 Btu
1 boiler hp33 475 Btu/h
1 in25.4 mm
1 ft304.8 mm
1 ft0.3048 m
1 yd0.9144 m
1 m3.281 ft
1 m39.37 in
1 km0.6214 mi
1 mi1.609 km
1 kg2.205 lb
1 lb0.4536 kg
1 lb16 oz
1 oz28.35 g
1 t (tonne)1 000 kg
1 t (tonne)2 205 lb
1 short ton2 000 lb
1 short ton907.2 kg
1 psi6.895 kPa
1 kPa0.1450 psi
1 bar100 kPa
1 bar14.50 psi
1 atm101.3 kPa
1 atm14.70 psi
1 in w.c.249.1 Pa
1 ft of water0.4335 psi
1 in Hg3.386 kPa
1 lbf4.448 N
1 kN224.8 lbf
°C to °F× 1.8, then + 32
°F to °C− 32, then ÷ 1.8
°C to K+ 273.15
A difference of 1 °C1.8 °F
Water freezes0 °C = 32 °F
Water boils (sea level)100 °C = 212 °F
1 km/h0.6214 mph
1 km/h0.2778 m/s
1 mph1.609 km/h
1 m/s3.281 ft/s
1 m/s196.9 ft/min
1 m/min3.281 ft/min
Electrical
Power (W)V × A
1 kW1 000 W
1 kVA1 000 VA
1 hp746 W
1 mA0.001 A
1 mV0.001 V
1 kΩ1 000 Ω
1 MΩ1 000 000 Ω
1 kWh1 kW for 1 hour
Power and energy
1 hp746 W
1 kW1.341 hp
1 kW3 412 Btu/h
1 Btu/h0.2931 W
1 Btu1.055 kJ
1 ton of refrigeration12 000 Btu/h
1 ton of refrigeration3.517 kW
1 kWh3.6 MJ
1 therm100 000 Btu
1 boiler hp33 475 Btu/h
Length
1 in25.4 mm
1 ft304.8 mm
1 ft0.3048 m
1 yd0.9144 m
1 m3.281 ft
1 m39.37 in
1 km0.6214 mi
1 mi1.609 km
Mass
1 kg2.205 lb
1 lb0.4536 kg
1 lb16 oz
1 oz28.35 g
1 t (tonne)1 000 kg
1 t (tonne)2 205 lb
1 short ton2 000 lb
1 short ton907.2 kg
Pressure and force
1 psi6.895 kPa
1 kPa0.1450 psi
1 bar100 kPa
1 bar14.50 psi
1 atm101.3 kPa
1 atm14.70 psi
1 in w.c.249.1 Pa
1 ft of water0.4335 psi
1 in Hg3.386 kPa
1 lbf4.448 N
1 kN224.8 lbf
Temperature
°C to °F× 1.8, then + 32
°F to °C− 32, then ÷ 1.8
°C to K+ 273.15
A difference of 1 °C1.8 °F
Water freezes0 °C = 32 °F
Water boils (sea level)100 °C = 212 °F
Speed
1 km/h0.6214 mph
1 km/h0.2778 m/s
1 mph1.609 km/h
1 m/s3.281 ft/s
1 m/s196.9 ft/min
1 m/min3.281 ft/min

On the exam

AcronymsYou get the list

Acronyms

30 acronyms

The following acronyms used in this trade may be on its Red Seal exam. They will also be provided with the exam sitting. The official list (PDF)

ACSRaluminum conductor steel reinforced
ASTMAmerican Society for Testing and Materials
BILbasic impulse insulation level
C.B.circuit breaker
CPRcardiopulmonary resuscitation
CTcurrent transformer
FRCflame retardant clothing
H.T.high tension
HIDhigh intensity discharge
HPShigh pressure sodium
K.V.F.W.kilovolt full wave
L.T.low tension
LLP/HOlive line permit/hold off
LMBload motorized break
LOA/MADlimit of approach/minimum approach distance
MVAmegavolt-ampere
N/Cnormally closed
N/Onormally open
OCRoil circuit recloser
PCBpolychlorinated biphenyls
PISApower-installed screw anchor
PPEpersonal protective equipment
PTpotential transformer
PVCpolyvinyl chloride
RBDradial boom derrick
RFradio frequency
RVMrecording voltmeter
ULFultra low frequency
VLFvery low frequency
XLPEcross-linked polyethylene
ACSRaluminum conductor steel reinforced
ASTMAmerican Society for Testing and Materials
BILbasic impulse insulation level
C.B.circuit breaker
CPRcardiopulmonary resuscitation
CTcurrent transformer
FRCflame retardant clothing
H.T.high tension
HIDhigh intensity discharge
HPShigh pressure sodium
K.V.F.W.kilovolt full wave
L.T.low tension
LLP/HOlive line permit/hold off
LMBload motorized break
LOA/MADlimit of approach/minimum approach distance
MVAmegavolt-ampere
N/Cnormally closed
N/Onormally open
OCRoil circuit recloser
PCBpolychlorinated biphenyls
PISApower-installed screw anchor
PPEpersonal protective equipment
PTpotential transformer
PVCpolyvinyl chloride
RBDradial boom derrick
RFradio frequency
RVMrecording voltmeter
ULFultra low frequency
VLFvery low frequency